Network Updates 22 May 2022

Bradfield build reaches Stacey Bank, Storrs and Dungworth

Our Bradfield FTTP build took a big step forward this weekend - after a number of digs along Loxley Road, we now have blown fibre tubing to Stacey Bank and most of the way to Storrs and Dungworth.

Bradfield build reaches Stacey Bank, Storrs and Dungworth

Our Bradfield FTTP build took a big step forward this weekend. After a number of digs along Loxley Road, we now have our blown fibre tubing reaching Stacey Bank, and most of the way to Storrs and Dungworth.

Customers connecting soon

With the duct infrastructure now in place, customers in these areas will start to receive their full fibre upgrade over the coming weeks. It's been a long time coming for many residents who have been waiting patiently for a proper broadband connection.

A growing rural network

This latest phase builds on the backhaul work we started in 2019 and the first customer connections in Worrall and Bradfield village. Each dig along Loxley Road extends our reach further into the valley, bringing Gigabit-capable broadband to communities that larger providers have overlooked.